Translate

Sep 9, 2018

First Flight of First Rafale for Indian Air Force

As the Rafale deal continues to be at the centre of a political maelstrom, only one of 36 Rafale fighter aircraft will be supplied from France to India until the end of the contract period in April 2022 with India-Specific Enhancements.
The balance 35 aircraft will start being delivered to India beginning September 2019 but they will be incorporated with these enhancements in India itself after the contract period at the rate of seven aircraft per month.
The “delivery of 36 Rafale aircraft in a fly-away condition along with associated equipment and weapons will commence from September 2019 and will be completed by April 2022.”
However, it will be only in September 2022 that the full complement of 36 Rafale aircraft will be available with IAF with the India-Specific Enhancements in place.
Government sources have often claimed that by negotiating a deal where the supply of 36 French jets would be completed by April 2022, it has saved five months off the UPA-era negotiations to meet the urgent operational requirements of the IAF.
indianexpress

No comments:

Post a Comment