Boeing’s KC-46 tanker program will miss a major contractual deadline to deliver 18 ready-to-go aircraft to the US Air Force next year.
Due to ongoing issues with the KC-46’s refueling systems, Boeing will not be able to deliver the 18 certified tankers to the Air Force as planned by August 2017, a major contractual obligation known as Required Assets Available, or RAA.
It is unclear what impact this delay will have on Boeing's contract to replace the Air Force's aging KC-135s. Both company and service officials said they are continuing to assess the implications.
defensenews